Current Progress
Remediation and Reclamation of Northwest Slopes of ČSA Open-pit Mine

Remediation and Reclamation of Northwest Slopes of ČSA Open-pit Mine

Opening date: 1. March 2011
Closing date: 1. October 2022
Spitzenberg Tunnel, A44 Highway, Germany

Spitzenberg Tunnel, A44 Highway, Germany

Opening date: 2. February 2017
Closing date: 31. December 2021
Railway Line Upgrade, Section Púchov - Žilina, Slovakia

Railway Line Upgrade, Section Púchov - Žilina, Slovakia

Opening date: 13. July 2016
Closing date: 31. January 2021
Railway Line Upgrade, Section Český Těšín - Dětmarovice

Railway Line Upgrade, Section Český Těšín - Dětmarovice

Opening date: 7. August 2017
Closing date: 7. April 2020
Herrschaftsbuck Tunnel, A98 Highway, Germany

Herrschaftsbuck Tunnel, A98 Highway, Germany

Opening date: 1. April 2017
Closing date: 30. January 2020
Reclamation of Podkrušnohorská Spoil Dump (Phase XII)

Reclamation of Podkrušnohorská Spoil Dump (Phase XII)

Opening date: 1. September 2009
Closing date: 31. December 2019
Railway Line Upgrade, Section Beroun – Králův Dvůr

Railway Line Upgrade, Section Beroun – Králův Dvůr

Opening date: 7. November 2016
Closing date: 7. November 2019
Railway Line Upgrade, Section Rokycany – Pilsen

Railway Line Upgrade, Section Rokycany – Pilsen

Opening date: 17. July 2013
Closing date: 17. August 2019