Cycle Route No.2950107 (line A 25) in Tunnel under Vítkov Hill, Prague

Investor:SŽDC s.o. a TSK hlavního města Prahy
Designer:SUDOP Praha a.s.
Contractor:Subterra a.s.
Implementation period:1. January 2010 - 30. April 2010
Cycle Route No.2950107 (line A 25) in Tunnel under Vítkov Hill, Prague

An old railway tunnel was restored – sediments from the vault were removed and damaged parts repaired, groundwater was prevented to leak in, drainage systems were restored and new finishes were done. When finished a cycle way was built (in the tunnel) including lighting.